Process Overview

A cable test programme translates the circuit drawing into defined checks and release criteria. Continuity identifies intended connections, while short-circuit and insulation checks address different requirements. Mechanical and sectioning checks can support the wider inspection plan where specified. Record the drawing revision, test configuration and batch identity so the result can be understood later, including when an installation issue needs investigation.

Electrical Testing process detail

Inspection & verification

  • iconCheck incoming wire, terminals and connectors against the approved material requirements
  • iconVerify preparation, crimp geometry and assembly details during production
  • iconRelease finished assemblies after continuity and any specified insulation checks
  • iconLink the agreed inspection results and test configuration to the production batch

iconTest Capabilities

Continuity coverage

100% finished-assembly continuity verification against the approved circuit map

High-potential testing

Up to 1,000 V DC on request; voltage, dwell and leakage limits agreed per assembly

Mechanical acceptance

Pull-force criteria follow the applicable terminal or joint specification

Traceability

Agreed batch, material-reel and inspection/test record references

iconEquipment

  • Automated continuity testers

    10 units for programmed multi-circuit connection checks

  • High-potential insulation testers

    4 units for specified dielectric-strength checks

  • Pull-force and peel testers

    3 units for the applicable mechanical verification

  • Micro-section preparation lab

    1 lab supporting crimp cross-section evaluation

Process Steps

Five controlled stages, each with a defined check before the batch moves on.

  1. 01

    Incoming verification

    Confirm component identification, material records and the applicable drawing revision.

  2. 02

    In-process checks

    Inspect the defined preparation, termination and assembly characteristics while production is running.

  3. 03

    Circuit testing

    Check intended connections and unintended shorts using the approved circuit map.

  4. 04

    Specified insulation checks

    Apply the agreed insulation or high-potential programme only where required by the specification.

  5. 05

    Record and release

    Review acceptance results and retain the required batch and test references before release.

Frequently Asked Questions

If your question is not answered here, the enquiry form below reaches the process engineers directly.

Is every finished assembly tested?

Finished assemblies receive continuity verification against the approved pinout. Other checks, including insulation resistance or high-potential testing, follow the drawing and agreed inspection plan rather than a single universal test setting.

Define the required records when requesting the quotation. The agreement should identify the recorded measurements, batch references, drawing revision and reporting format so the production release includes the documentation your team needs.

IQC covers incoming material verification, IPQC covers checks during production, and OQC covers outgoing release inspection. The characteristics and sampling or coverage at each stage should be established for the particular assembly.

An assembly or batch identifier provides a starting point for reviewing material references, drawing revisions and available inspection records. Share the failure circumstances and identification so the relevant production window and test configuration can be examined.

Discuss Your Sample Requirements

Send a drawing or a sample and we will build a first article to the agreed inspection plan so you can validate the process before committing to volume.

Tell us what you need to build

Send a drawing, a BOM, a part number or just one sentence. Our engineers review every enquiry and reply within 24 hours.

  • Engineering review within 24 hours
  • NDA available before drawings are shared
  • Free samples in 5-7 days after drawing approval
Inquiry Drawer

Review & Submit Request

This site uses cookies

We use cookies to collect information about how you use this site. We use this information to make the website work as well as possible and improve our services.more details